Friday, July 27, 2012

Thursday, November 3, 2011

Blowers

Almost hard to recognize the old blower room nowadays.

Boilers Boiling

Our first day of real cold (high only mid 40s today) and the new units are taking care of business. Still need some balancing in rooms, though. Too hot in some, too cold in others.

Update

The new drop ceiling in the hallway looks good (and hides all of the pipes).

Tuesday, September 27, 2011

Blower Room

Circulation pumps are running today. Hopefully testing out some equipment tonight.

Friday, September 23, 2011

Hallway

The library hallway is supposed to get a drop ceiling added to cover all of this new stuff. The air handler up there is just about finished with the wiring.

Growth Continues

More progress on the ceilng work.

Big Day

Pipe commissioning is supppsed to be today (I believe this is where the phrase 'in commission' comes from). That means we are getting really close to being able to turn on heat at will. As you can see the new boilers are much smaller than the old ones.

Friday, September 9, 2011

Piped

Most of the classes have their units piped this week. Getting better every day!

Wednesday, September 7, 2011

Condensers

These came in this week. Glad we don't really need them so much anymore!

Monday, August 29, 2011

Hooray For Cranes!

Amazing job going on today. This is the main chiller for the building.

Thursday, August 18, 2011

New Enrollees

We are VERY happy to see these new arrivals to the school. They were all brought in yesterday.

Monday, August 15, 2011

Thursday, August 11, 2011

Finished Looking

So this is what all the fuss is about...

We Have Struck Room!

After digging through, we discovered that things are looking way better.

New Transformer

CU set the new box this week. We're getting ready for the switchover.

Monday, August 8, 2011

Superheroes!

Custodial crew started working on the rooms this week. 304 is already looking good. Amazing what they are getting done when we didn't know how it could get done!

Chiller Pad

Fencing prep for the (not yet here) chiller.

Closet in 208

Mrs. Barge's closet as a sample of what they will end up looking like.

Lab

Lab ceiling exists once more!

Library

Ceiling is coming back together in the library now.