Boyd Air Conditioning Project
A record of the air conditioning installation project at Boyd Elementary. Established in 1908, and re-built in 1911 the school will be receiving air conditioning for the first time during the second half of 2011.
Monday, August 6, 2012
Thursday, August 2, 2012
Friday, July 27, 2012
Tuesday, July 24, 2012
Tuesday, July 17, 2012
Thursday, July 12, 2012
Monday, July 9, 2012
Thursday, November 3, 2011
Boilers Boiling
Our first day of real cold (high only mid 40s today) and the new units are taking care of business. Still need some balancing in rooms, though. Too hot in some, too cold in others.
Tuesday, September 27, 2011
Friday, September 23, 2011
Hallway
The library hallway is supposed to get a drop ceiling added to cover all of this new stuff. The air handler up there is just about finished with the wiring.
Big Day
Pipe commissioning is supppsed to be today (I believe this is where the phrase 'in commission' comes from). That means we are getting really close to being able to turn on heat at will. As you can see the new boilers are much smaller than the old ones.
Friday, September 9, 2011
Wednesday, September 7, 2011
Monday, August 29, 2011
Thursday, August 18, 2011
Monday, August 15, 2011
Chiller Pad
Emergency generator and fencing was installed this last week. The new transformer is going up today.
Thursday, August 11, 2011
Monday, August 8, 2011
Superheroes!
Custodial crew started working on the rooms this week. 304 is already looking good. Amazing what they are getting done when we didn't know how it could get done!
Monday, August 1, 2011
Tuesday, July 26, 2011
More Prep Work
Ducts are just about complete now. The room in the foreground being jackhammered will be for the inside air handlers. Where there used to be a water fountain and ice maker, there will now be doors. We will relocate the other items.
Projections right now are that staff will be able to get back in the week before school starts. It will be tight, for sure!